Meeting December 16, 2010

LVL1 White Star Balloon

  1. Workload Impressions
    1. Amphetamines
    2. Better heat
    3. We were setting dates without having accurate estimate of workload estimate.
    4. Have more regular “are we ready” meeting checkins
    5. SpeedBall-2 will be easier than 1
    6. Keep eachother apprised of what the estimation is
    7. More clearly define what the go/nogo parameters are, and what will need to be done to get there
    8. Spend more time documenting progress
    9. Set large visual milestones clearly to see where progress status is
    10. Revisit SCRUM - based on “what's the bare minimum necessary to get to goal”
    11. Ask people directly if they will get specific things done.
    12. Launch date doesn't necessarily help to motivate. Have detailed checklist of items to check off that leads to fulfill launch requirements instead of hard launch date.
      1. Need to pick intermediate milestones and review them
      2. Have to assemble balloon - need to pick date to actually put all systems together
      3. Envelope
        1. receive
        2. Figure tests
        3. Test
        4. Launch
      4. Payloads
        1. Hardware, Software, Testing, Integration, Assemble
        2. Flight Control Box
          1. Power Control
          2. Flight Control
          3. Ballast
          4. Etc
        3. Ballast
      5. Ground Support track
      6. Mission Control Track
      7. Web Track
  2. Progress Remaining
    1. Software
      1. Comm Controller 95%
      2. Flight Computer 95%
    2. Web
      1. Database? 90%
      2. Mission Control Page? - Ping Todd Hudgens 0%
      3. ATC Page? - Ping Todd Hudgens 0%
    3. Hardware
      1. Payload Box? 10%
      2. Rigging lines? 10%
      3. Ballast Bottle? 90%
    4. Documentation
      1. ATC procedures 50%
        1. Will have meeting Saturday
      2. Launch Procedure - 30%
      3. Safety Manual - 40%
      4. Flight Rules - 60%
      5. Mission Control position guides %50
  3. Review Parts Needed yet for SB-1
    1. Power controller rebuild.
      1. Pololu 2 Volt regulators
  4. Order Parts
agendas/20101216.txt · Last modified: 2010/12/17 03:47 by steamfire
 
Except where otherwise noted, content on this wiki is licensed under the following license: CC Attribution-Share Alike 3.0 Unported
Recent changes RSS feed Donate Powered by PHP Valid XHTML 1.0 Valid CSS Driven by DokuWiki